In October 2019, we sawed Jantje in half. After months of drawing, saving, planning and calculating, we concluded that extending the ship was the only way to future-proof both the vessel and the business.
Here are some photos of this massive project.
The refit in numbers
Days: 237
Work hours: ± 10,000
Cost: ± €220,000
New steel: 10 tonnes
Extra ballast: 16 tonnes
Construction vacuums: 4
Number of frikandellen: see work hours
Workers: Erik, Marten, Yim, Peter, Gabriel, Claire, Marijn, Niklas, Sven, Richard, Roland, Diederik, Giel, Willemien, Arnold, Fieke, Ton, Jur, Teun, Henk, Josefien