Extension

In October 2019 we saw Jantje in half. After drawing, saving, planning and calculating for a long time, we concluded that an extension was the only way to make the ship - and thus the company - future-proof.

Some images of this tremendous job.

Days: 237



Working hours: ± 10.000



Costs: ± € 220.000



New steel: 10 tons



Additional counterweight: 16 tons



Construction vacuum cleaners: 4



Number of frikadels: see working hours



Workers: Erik, Marten, Yim, Peter, Gabriel, Claire, Marijn, Niklas, Sven, Richard, Roland, Diederik, Giel, Willemien, Arnold, Fieke, Ton, Jur, Teun, Henk, Josefien